Adani Power Project in Satara Faces Fresh Scrutiny as Excavation Continues in Fifth Village Beyond Four Approved Villages

By Raju Saha • 21/11/2026

A major environmental and regulatory controversy has erupted over Adani Green Energy Limited proposed hydropower project in Maharashtra Satara district after fresh complaints accused the developer of carrying out unauthorized excavation in a village outside its approved project area. While the central environmental clearance granted to the 1,500 megawatt Tarali Pumped Storage Project covered only four specific villages, digging and development work were found underway in a fifth village without required permissions.

According to project records, the Union Ministry of Environment, Forest and Climate Change had granted environmental clearance on February 11, 2025, for the open-loop pumped storage project across 150.74 hectares of non-forest land. That official nod specifically covered four villages in Patan taluka of Satara district, namely Nivade, Tondoshi, Kalambe, and Jalu. However, honorary wildlife warden Rohan Bhate filed a formal complaint with the Maharashtra Pollution Control Board pointing out that large-scale soil excavation and construction work had started in Sawarghar village, which was never included in the original clearance.

Following a site inspection carried out by officials in Satara on Friday, November 20, 2026, the Maharashtra Pollution Control Board issued an official letter directing Adani Green Energy Limited to immediately halt all excavation and development work in Sawarghar village. The pollution control board noted in its communication that the digging at Sawarghar was being carried out without obtaining mandatory consent from the board and without valid environmental clearance for that location.

The dispute carries heightened ecological sensitivity because the proposed project lies within the deemed eco-sensitive zone surrounding the Koyna Wildlife Sanctuary and the Sahyadri Tiger Reserve. In his representation to state authorities, Rohan Bhate stressed that any unapproved digging or construction so close to protected tiger and wildlife habitats poses serious environmental risks. He also urged officials to verify whether prior approval had been obtained from the Standing Committee of the National Board for Wildlife, known as NBWL, and demanded an independent inquiry by a higher authority rather than local officials linked to earlier clearances.

This latest action by the pollution board comes just days after the Maharashtra forest department issued its own stop-work directive on November 13, 2026. Satara Deputy Conservator of Forests Amol Satpute had ordered the company to pause project activities after observing that work had begun without mandatory prior clearance from the National Board for Wildlife. Sources indicated that excavation had continued despite the November 13 forest department notice, prompting officials to check whether the developer violated earlier directions.

On its part, Adani Green Energy Limited has maintained in earlier statements that no part of the Tarali project falls inside a notified protected area and that the project does not use forest land. The company stated that its proposal seeking wildlife board clearance had already been submitted and was under official review, while adding that site survey and investigation activities had been recommended earlier by the state wildlife board.

Meanwhile, discontent on the ground has continued to grow among local villagers, farmers, and environmental activists across Patan taluka. Residents from nearby villages such as Dafarwadi, Kenjalwadi, and Kalambe have raised serious concerns that blasting and excavation work for the hydropower project could damage natural springs and local drinking water sources. Following a joint meeting with villagers, government officials, and company representatives on November 21, 2026, Maharashtra Minister Shambhuraj Desai acknowledged that local grievances had not yet been resolved and announced that another round of talks would be held.

For rural communities living along the edge of the Western Ghats in Satara, protecting village water sources, farmland, and forest corridors remains a top priority. With both the forest department and the Maharashtra Pollution Control Board stepping in to halt unauthorized digging, state authorities now face mounting public pressure to enforce strict environmental rules before any further construction moves forward.